Expected on 28 April to demolish the remains of the Office of the Auditor General building up to the 1st floor - 1 more person found trapped

The demolition section has now reduced the height to approximately 2.50 meters. It is expected that on April 28, the area down to the first floor will be opened, which will increase the number of drilling machines. In addition, more people have been added to support the steel cutting work. The demolition will be carried out in all areas simultaneously to allow the drilling work to proceed faster. As for the removal of the scraps of the Office of the Auditor General of Thailand building that were demolished to the scrap disposal point, 343 trips have been completed.